Capital Projects

The Engineering Department has been implementing projects from the 2008-2012 Capital Improvement Program, in the area of public infrastructure (roads, utilities and drainage). The ever-increasing challenges of a thriving and growing community have necessitated improvements in all categories.
  1. ROADS
  2. Utilities
  3. Facilities
  4. Future
  5. Maps
Lanes.png

Alma Drive Improvements


(Hedgcoxe to SH 121) 
Project Manager: Kevin Bates
  Ridgeview Drive, Phase 2
(Watters to Chelsea)
Project Manager: Kevin Bates
  •  Includes 6-lane bridge across Cottonwood Creek
  • Completion anticipated August 2018 
Stacy Road

Stacy Road


(Greenville Ave to FM 1378)
Project Contact: Joseph Cotton
 
  • TxDOT project currently in design
  • Paving will begin April 3, 2017 - Expect delays from construction traffic
  • Anticipated completion January 2018       
US 75

US 75


(Spring Creek Pkwy to Collin County Line)
Project Contact: Chris Flanigan
Planning continues on this important roadway segment as the communities of Allen, Anna, Melissa, Fairview, McKinney and Plano look towards the ultimate improvement of this roadway, with 8 main lanes and HOV lanes. 

  • TxDOT project adding 2 additional lanes and ramp improvements.
  • Project is substantially complete and all lanes are open to traffic. There may be occasional temporary lane closures while contractor is working on punch list items and landscaping.